PRINCE2 7 Foundation
Free PRINCE2 7 Foundation study guide and exam blueprint. 60 questions in 60 minutes, 60% to pass. Written from PeopleCert's PRINCE2 7 syllabus, last checked 27 July 2026. Domain weightings, glossary, and practice questions with worked explanations.
PRINCE2 is a defined method with named parts, and Foundation tests whether you know the parts and what they are called. This is not a judgement exam. Almost nobody fails it for lacking project experience. They fail it for not learning the vocabulary precisely enough to tell two similar terms apart under time pressure.
Most exams in this catalogue reward judgement: several options are defensible and you choose the best. PRINCE2 Foundation does not work that way. The method defines its own terms, and the exam checks whether you know them. A question will ask which principle applies, which process produces a particular product, or which role holds a specific responsibility. There is one right answer and it is written down in the manual.
That makes this exam learnable in a way that judgement exams are not. The work is precision, not experience. The trap is the opposite of the PMP trap: instead of overthinking, candidates skim, assume two similar terms mean the same thing, and lose marks on distinctions that are entirely mechanical once learned.
The official weightings are unusually lopsided, and it changes how you should revise. The practices are 60% of the paper, roughly 36 of the 60 questions. Everything else combined is the other 40%. Key concepts is 3%, which is about two questions on the whole paper.
So: if your revision time is limited, spend it on the seven practices. Learning the key concepts section perfectly earns you two marks. Learning the practices section perfectly earns you thirty-six.
PRINCE2 7 was released in September 2023 and is what you will sit. It is not a light refresh, and material written for the 6th edition will actively mislead you:
Five learning outcomes with published weightings. One of them is 60% of the paper, which makes this the most lopsided blueprint of any exam here, and the easiest to revise strategically.
Read that bar again. Practices alone are more than half the exam. Practices and processes together are 75%. If you learn nothing else properly, learn the seven practices: what each one is for, what it produces, and which role is accountable.
| Outcome | Weight | Roughly | What it covers |
|---|---|---|---|
| 1. Key concepts | 3% | 2 qs | What a project is, the five integrated elements, the seven performance aspects, outputs against outcomes against benefits. |
| 2. Principles | 8% | 5 qs | The seven principles and what each one requires. |
| 3. People | 14% | 8 qs | New in PRINCE2 7. Leading and managing people, change management, communication, culture. |
| 4. Practices | 60% | 36 qs | The seven practices: business case, organizing, plans, quality, risk, issues, progress. |
| 5. Processes | 15% | 9 qs | The seven processes, their purpose, and which management products they produce. |
| Questions | 60, all multiple choice, four options, one correct. |
| Time | 60 minutes. One minute per question. |
| Pass mark | 60%, so 36 correct. Raised from 55% in earlier editions. |
| Book | Closed. Nothing is allowed in with you. |
| Marking | One mark per question, no negative marking. Never leave a blank. |
| Prerequisite | None. Anyone may sit Foundation. |
| Delivery | Online proctored through PeopleCert, or at a test centre. |
| Validity | Three years, then renew through PeopleCert Plus CPD points or by re-sitting. |
Only about two questions, but it is the vocabulary the other 58 are written in. Learn it quickly and move on. Do not spend a weekend here.
A project is a temporary organisation created for the purpose of delivering one or more business products according to an agreed business case. Note "temporary organisation", not "temporary endeavour". PRINCE2 treats a project as a structure of people with defined roles, which is why organising is one of the seven practices.
Projects are distinguished from business as usual by five characteristics: change, temporary, cross-functional, unique, and uncertainty.
PRINCE2 7 is built from five elements that work together. Learn these five words in order; questions frequently ask which element something belongs to.
| Element | What it is |
|---|---|
| Principles | Seven guiding obligations. A project is only a PRINCE2 project if all seven are applied. |
| People | New in version 7. The human side: leading, managing change, communicating, building culture. |
| Practices | Seven aspects that must be addressed continually throughout the project. Formerly called themes. |
| Processes | Seven sets of activities that carry the project from before it starts through to closure. |
| Project context | The environment the project sits in, which drives how the method is tailored. |
A favourite exam distinction, and worth getting exactly right because the three are easy to blur.
| Term | Meaning | Example |
|---|---|---|
| Output | A specialist product the project delivers. | A new booking system. |
| Outcome | The result of the change derived from using the output. | Staff book appointments digitally rather than on paper. |
| Benefit | The measurable improvement resulting from an outcome, perceived as an advantage by a stakeholder. | Administration time falls by 30%. |
The chain runs output leads to outcome leads to benefit. Projects deliver outputs. Benefits are usually realised after the project closes, which is why benefits management continues beyond it.
Seven obligations, roughly five questions. They are the definition of what makes a project a PRINCE2 project: all seven must be applied, or it is not PRINCE2. Learn them by name, in order, and know what each one actually demands.
| Principle | What it requires |
|---|---|
| 1. Ensure continued business justification | There must be a justifiable reason to start the project, and it must remain valid throughout. If justification disappears, the project should be stopped. This is why the business case is reviewed at every stage boundary, not written once and filed. |
| 2. Learn from experience | Lessons are sought, recorded and acted on throughout. A lessons log is opened when the project starts up, and a lessons report is produced at closure. |
| 3. Define roles, responsibilities and relationships | Everyone knows what they are accountable for and who they answer to. The project management team structure is explicit, and the three primary stakeholder interests (business, user, supplier) are all represented. |
| 4. Manage by stages | The project is planned, monitored and controlled stage by stage. There is a minimum of two stages: the initiation stage and at least one further delivery stage. |
| 5. Manage by exception | Tolerances are set for each objective. Within tolerance, the level below gets on with the work unsupervised. Only when a tolerance is forecast to be exceeded does the situation escalate. This is what makes PRINCE2 efficient for senior management. |
| 6. Focus on products | The project concentrates on the definition and delivery of products, particularly their quality requirements. Agree what is being produced before deciding how much effort it takes. |
| 7. Tailor to suit the project | PRINCE2 is adapted to the project's context: size, complexity, importance, team capability and risk. Tailoring is mandatory, not optional. |
Manage by exception is the one candidates most often misread. It does not mean escalating problems. It means not escalating anything that stays within agreed tolerance, so management time is spent only where a decision is genuinely needed. Tolerances are set against all seven performance aspects, at project, stage and team level.
Continued business justification is the one that produces the "what should happen next" questions. If the business case is no longer valid, the correct PRINCE2 answer is almost always that the project should be closed, even mid-delivery. Sunk cost is not a justification.
New in PRINCE2 7, and worth 14% on its own, which is nearly twice the principles. Any material written for the 6th edition will not cover this at all. That makes it both a common gap and an easy source of marks.
PRINCE2 distinguishes the two deliberately. Leading is about direction, influence and motivation: setting a vision people will follow. Managing is about organising and controlling work so it gets done. A project manager needs both, and the balance shifts with the situation.
The method notes that leadership is not tied to authority. Influence, credibility and the ability to build trust matter more than position, which is why a project manager with no line authority can still lead effectively.
A crucial distinction, and one the exam tests: change management here means helping people adopt a change, not the change control procedure that handles issues and requests for change. Those are different things with confusingly similar names.
Projects produce outputs, but benefits only arrive when people actually work differently. If nobody adopts the new system, the outcome never happens and the benefit is never realised. That is why change management sits alongside delivery rather than after it.
PRINCE2 7 expects awareness of how project teams form and develop, how capability is built, and how motivation is sustained across a temporary organisation where people are often borrowed from elsewhere. The practical point the exam draws on: because a project team is temporary and cross-functional, the effort of forming it, agreeing how it will work, and disbanding it deliberately at closure is part of the work, not an overhead.
Sixty per cent of the paper, roughly 36 of the 60 questions. If your revision time is short, this section is where all of it should go. Formerly called themes; the rename is the clearest signal of whether a resource is current.
| Practice | Answers the question | Key products |
|---|---|---|
| Business case | Why? | Business case, benefits management approach |
| Organizing | Who? | Project management team structure, role descriptions, communication management approach |
| Plans | How, how much, when? | Project plan, stage plans, team plans, exception plan, product descriptions |
| Quality | What is good enough? | Quality management approach, quality register, product descriptions |
| Risk | What if? | Risk management approach, risk register |
| Issues | What is the impact? | Issue management approach, issue register, issue reports |
| Progress | Where are we? Should we continue? | Daily log, lessons log, highlight reports, checkpoint reports, end stage reports |
Establishes and maintains the justification. Owned by the executive, who is accountable for it throughout. Developed in outline during starting up a project, detailed during initiating a project, and reviewed at every stage boundary, because justification must remain valid, not merely have existed once.
The benefits management approach defines how and when benefits will be measured, and it survives the project: benefits are usually realised after closure, so someone must own their measurement afterwards.
Defines the temporary organisation. The structure has four levels, and the exam tests them constantly.
| Level | Who | Responsibility |
|---|---|---|
| Commissioning | Corporate, programme management or the customer | Sits outside the project, commissions it, sets constraints and appoints the executive. |
| Directing | Project board | Accountable for the project's success. Makes the go or no-go decisions. |
| Managing | Project manager | Runs the project day to day on behalf of the board, within agreed tolerances. |
| Delivering | Team manager and team members | Produces the specialist products to the agreed quality. |
The project board holds three roles representing the three stakeholder interests: the executive (business interest, ultimately accountable, and the only role that cannot be shared), the senior user (specifies needs and is accountable for realising benefits), and the senior supplier (provides resources and technical expertise). Project assurance is the board's independent check and cannot be delegated to the project manager. Project support is administrative help and may be shared or delegated.
PRINCE2 plans are product-based. You define the products first, then the activities needed to create them, then the effort. The four plan types: project plan (the whole, owned by the board), stage plan (one management stage, the project manager's working document), team plan (optional, for a work package), and exception plan (replaces a plan that is forecast to breach tolerance, and is approved at the level that set the tolerance).
Product-based planning has four steps: write the project product description, create the product breakdown structure, write product descriptions, then create the product flow diagram showing the sequence and dependencies.
Two ideas the exam loves to separate. Quality planning defines what "fit for purpose" means: quality criteria go into product descriptions, and acceptance criteria into the project product description. Quality control checks that products meet them, and records results in the quality register.
Also distinguish quality assurance (an organisational function, independent of the project, checking the project is being run properly) from project assurance (the project board's own independent check). They are different, and questions exploit the similarity.
A risk is an uncertain event that, should it occur, will affect the achievement of objectives. Risks are threats (negative) or opportunities (positive). The recommended procedure has five steps: identify, assess, plan, implement, with communicate running throughout rather than as a final step.
| Responses to threats | Responses to opportunities |
|---|---|
| Avoid, reduce, transfer, share, accept, prepare contingent plans | Exploit, enhance, share, reject |
Risk owner manages and monitors a risk; risk actionee carries out the response action. They may be the same person but are defined separately, and the exam asks.
An issue is anything happening now that needs addressing, as opposed to a risk, which might happen. Three types: a request for change, an off-specification (a product that does not or will not meet its specification), and a problem or concern (anything else).
Handled either formally in the issue register, or informally in the daily log if minor. Change authority is the role that decides on requests for change, and a change budget may be set aside to fund approved ones.
Answers whether the project is on track and should continue. It rests on tolerances (permitted deviation before escalation, set against all seven performance aspects at project, stage and team level) and on regular reporting.
| Report | From | To |
|---|---|---|
| Checkpoint report | Team manager | Project manager |
| Highlight report | Project manager | Project board |
| Exception report | Project manager | Project board, when tolerance is forecast to be exceeded |
| End stage report | Project manager | Project board, at a stage boundary |
| End project report | Project manager | Project board, at closure |
Roughly nine questions. The processes are the timeline: what happens, in what order, and who does it. Learn the purpose of each and which management products it produces, and most questions answer themselves.
| Process | Purpose | Owner |
|---|---|---|
| Starting up a project | Decide whether the project is worthwhile and viable. Pre-project: it happens before the project is authorised. | Executive and project manager |
| Directing a project | Enable the board to be accountable through key decisions, while delegating day-to-day management. Runs the entire length of the project. | Project board |
| Initiating a project | Establish solid foundations: agree how the project will be run and produce the PID. | Project manager |
| Controlling a stage | Assign and monitor work, deal with issues, report progress within the current stage. | Project manager |
| Managing product delivery | Control the link between project manager and team, and produce the specialist products. | Team manager |
| Managing a stage boundary | Report on the stage just finished, plan the next one, and update the business case so the board can decide whether to continue. | Project manager |
| Closing a project | Confirm the products are accepted and the project's objectives met, then close it in an orderly way. | Project manager |
Every PRINCE2 project has at least two management stages: the initiation stage and at least one delivery stage. That follows directly from the manage by stages principle, and it is a frequent exam check.
The board's decision points sit at stage boundaries, which is what makes stages the control mechanism rather than an administrative convenience.
The defined terms this exam is built from, grouped so the ones that get confused sit next to each other.
The PRINCE2 7 Foundation exam has 60 questions and lasts 60 minutes. You need 60% to pass.
The exam covers 5 domains: Key concepts (3%), Principles (8%), People (14%), Practices (60%), Processes (15%). These weightings come from PeopleCert's PRINCE2 7 syllabus.
Yes. This guide was written from PeopleCert's own published outline, PRINCE2 7 syllabus, and last checked against that document on 27 July 2026. That date is shown on every page so you can judge for yourself rather than take our word for it.
Yes. Sample questions with full worked explanations are free and need no account. The complete question bank and the full-length 60-question timed mock are paid.
The guide above is free. The question bank and the full-length timed mock are the paid part.
Open PRINCE2 →Cutscores is independent and is not affiliated with, authorised by, endorsed by or sponsored by PeopleCert or any certification body. PRINCE2 and all certification names and marks are the property of their respective owners, and are used here only to describe which exam this material prepares you for. We do not reproduce live exam content.