PeopleCert · free study guide

PRINCE2 7 Foundation study guide

PRINCE2 7 Foundation

Free PRINCE2 7 Foundation study guide and exam blueprint. 60 questions in 60 minutes, 60% to pass. Written from PeopleCert's PRINCE2 7 syllabus, last checked 27 July 2026. Domain weightings, glossary, and practice questions with worked explanations.

Written from PeopleCert's PRINCE2 7 syllabus. Last checked against that document on 27 July 2026.
60 questions 60 minutes 60% to pass 5 domains
Orientation

A method, not a philosophy.

PRINCE2 is a defined method with named parts, and Foundation tests whether you know the parts and what they are called. This is not a judgement exam. Almost nobody fails it for lacking project experience. They fail it for not learning the vocabulary precisely enough to tell two similar terms apart under time pressure.

The 60-60-60 rule
60 questions, 60 minutes, 60% to pass. That is 36 correct out of 60, at exactly one minute per question. Closed book. Four options, one correct answer, one mark each, and no negative marking, so never leave anything blank. A guess costs you nothing and might earn a mark.

What makes this exam different

Most exams in this catalogue reward judgement: several options are defensible and you choose the best. PRINCE2 Foundation does not work that way. The method defines its own terms, and the exam checks whether you know them. A question will ask which principle applies, which process produces a particular product, or which role holds a specific responsibility. There is one right answer and it is written down in the manual.

That makes this exam learnable in a way that judgement exams are not. The work is precision, not experience. The trap is the opposite of the PMP trap: instead of overthinking, candidates skim, assume two similar terms mean the same thing, and lose marks on distinctions that are entirely mechanical once learned.

Where the marks actually are

The official weightings are unusually lopsided, and it changes how you should revise. The practices are 60% of the paper, roughly 36 of the 60 questions. Everything else combined is the other 40%. Key concepts is 3%, which is about two questions on the whole paper.

So: if your revision time is limited, spend it on the seven practices. Learning the key concepts section perfectly earns you two marks. Learning the practices section perfectly earns you thirty-six.

PRINCE2 7, and why the edition matters

PRINCE2 7 was released in September 2023 and is what you will sit. It is not a light refresh, and material written for the 6th edition will actively mislead you:

Your study plan

Official syllabus

What the exam is made of.

Five learning outcomes with published weightings. One of them is 60% of the paper, which makes this the most lopsided blueprint of any exam here, and the easiest to revise strategically.

3%Key concepts8%Principles14%People60%Practices15%Processes
Five learning outcomes 60 questions · 60 minutes

Read that bar again. Practices alone are more than half the exam. Practices and processes together are 75%. If you learn nothing else properly, learn the seven practices: what each one is for, what it produces, and which role is accountable.

The five learning outcomes

OutcomeWeightRoughlyWhat it covers
1. Key concepts3%2 qsWhat a project is, the five integrated elements, the seven performance aspects, outputs against outcomes against benefits.
2. Principles8%5 qsThe seven principles and what each one requires.
3. People14%8 qsNew in PRINCE2 7. Leading and managing people, change management, communication, culture.
4. Practices60%36 qsThe seven practices: business case, organizing, plans, quality, risk, issues, progress.
5. Processes15%9 qsThe seven processes, their purpose, and which management products they produce.

The format

Questions60, all multiple choice, four options, one correct.
Time60 minutes. One minute per question.
Pass mark60%, so 36 correct. Raised from 55% in earlier editions.
BookClosed. Nothing is allowed in with you.
MarkingOne mark per question, no negative marking. Never leave a blank.
PrerequisiteNone. Anyone may sit Foundation.
DeliveryOnline proctored through PeopleCert, or at a test centre.
ValidityThree years, then renew through PeopleCert Plus CPD points or by re-sitting.
Foundation is the gateway
You cannot sit PRINCE2 Practitioner without passing Foundation first. Practitioner is a different animal: 70 questions in 150 minutes, open book against the official manual, and scenario-based rather than definitional. Foundation asks what a thing is. Practitioner asks whether you can apply it to a described situation.
Outcome 1 3%

Key concepts.

Only about two questions, but it is the vocabulary the other 58 are written in. Learn it quickly and move on. Do not spend a weekend here.

What PRINCE2 means by a project

A project is a temporary organisation created for the purpose of delivering one or more business products according to an agreed business case. Note "temporary organisation", not "temporary endeavour". PRINCE2 treats a project as a structure of people with defined roles, which is why organising is one of the seven practices.

Projects are distinguished from business as usual by five characteristics: change, temporary, cross-functional, unique, and uncertainty.

The five integrated elements

PRINCE2 7 is built from five elements that work together. Learn these five words in order; questions frequently ask which element something belongs to.

ElementWhat it is
PrinciplesSeven guiding obligations. A project is only a PRINCE2 project if all seven are applied.
PeopleNew in version 7. The human side: leading, managing change, communicating, building culture.
PracticesSeven aspects that must be addressed continually throughout the project. Formerly called themes.
ProcessesSeven sets of activities that carry the project from before it starts through to closure.
Project contextThe environment the project sits in, which drives how the method is tailored.

The seven performance aspects

Sustainability is the one people forget
There are seven aspects of project performance to be managed: benefits, cost, time, quality, scope, sustainability, and risk. Sustainability was added in PRINCE2 7. Older material lists six and omits it, which is precisely why the exam likes asking. Tolerances are set against all seven.

Outputs, outcomes and benefits

A favourite exam distinction, and worth getting exactly right because the three are easy to blur.

TermMeaningExample
OutputA specialist product the project delivers.A new booking system.
OutcomeThe result of the change derived from using the output.Staff book appointments digitally rather than on paper.
BenefitThe measurable improvement resulting from an outcome, perceived as an advantage by a stakeholder.Administration time falls by 30%.

The chain runs output leads to outcome leads to benefit. Projects deliver outputs. Benefits are usually realised after the project closes, which is why benefits management continues beyond it.

Two more distinctions worth banking

Outcome 2 8%

The seven principles.

Seven obligations, roughly five questions. They are the definition of what makes a project a PRINCE2 project: all seven must be applied, or it is not PRINCE2. Learn them by name, in order, and know what each one actually demands.

The rule that makes them testable
The principles are universal (they apply to every project), self-validating (proven over years of practice), and empowering (they give practitioners confidence and ability to shape the method). Unlike practices and processes, principles are never tailored. You tailor how you apply them; you never drop one.

The seven, in order

PrincipleWhat it requires
1. Ensure continued business justificationThere must be a justifiable reason to start the project, and it must remain valid throughout. If justification disappears, the project should be stopped. This is why the business case is reviewed at every stage boundary, not written once and filed.
2. Learn from experienceLessons are sought, recorded and acted on throughout. A lessons log is opened when the project starts up, and a lessons report is produced at closure.
3. Define roles, responsibilities and relationshipsEveryone knows what they are accountable for and who they answer to. The project management team structure is explicit, and the three primary stakeholder interests (business, user, supplier) are all represented.
4. Manage by stagesThe project is planned, monitored and controlled stage by stage. There is a minimum of two stages: the initiation stage and at least one further delivery stage.
5. Manage by exceptionTolerances are set for each objective. Within tolerance, the level below gets on with the work unsupervised. Only when a tolerance is forecast to be exceeded does the situation escalate. This is what makes PRINCE2 efficient for senior management.
6. Focus on productsThe project concentrates on the definition and delivery of products, particularly their quality requirements. Agree what is being produced before deciding how much effort it takes.
7. Tailor to suit the projectPRINCE2 is adapted to the project's context: size, complexity, importance, team capability and risk. Tailoring is mandatory, not optional.

The two that generate the most questions

Manage by exception is the one candidates most often misread. It does not mean escalating problems. It means not escalating anything that stays within agreed tolerance, so management time is spent only where a decision is genuinely needed. Tolerances are set against all seven performance aspects, at project, stage and team level.

Continued business justification is the one that produces the "what should happen next" questions. If the business case is no longer valid, the correct PRINCE2 answer is almost always that the project should be closed, even mid-delivery. Sunk cost is not a justification.

A question pattern to expect
"A project continues even though the expected benefits can no longer be achieved. Which principle is being breached?" The answer is ensure continued business justification. Similar stems test whether you can map a described failure back to the principle it violates, so practise reading each principle as a rule that can be broken.
Outcome 3 14%

People.

New in PRINCE2 7, and worth 14% on its own, which is nearly twice the principles. Any material written for the 6th edition will not cover this at all. That makes it both a common gap and an easy source of marks.

Why it was added
Earlier editions treated projects almost purely as structures and processes. PRINCE2 7 raises people to one of the five integrated elements, on the basis that methods do not deliver projects, people do. Expect questions on leadership, change management, communication and culture, framed in PRINCE2's own vocabulary.

Leading and managing

PRINCE2 distinguishes the two deliberately. Leading is about direction, influence and motivation: setting a vision people will follow. Managing is about organising and controlling work so it gets done. A project manager needs both, and the balance shifts with the situation.

The method notes that leadership is not tied to authority. Influence, credibility and the ability to build trust matter more than position, which is why a project manager with no line authority can still lead effectively.

Change management

A crucial distinction, and one the exam tests: change management here means helping people adopt a change, not the change control procedure that handles issues and requests for change. Those are different things with confusingly similar names.

Projects produce outputs, but benefits only arrive when people actually work differently. If nobody adopts the new system, the outcome never happens and the benefit is never realised. That is why change management sits alongside delivery rather than after it.

Culture, collaboration and communication

Teams

PRINCE2 7 expects awareness of how project teams form and develop, how capability is built, and how motivation is sustained across a temporary organisation where people are often borrowed from elsewhere. The practical point the exam draws on: because a project team is temporary and cross-functional, the effort of forming it, agreeing how it will work, and disbanding it deliberately at closure is part of the work, not an overhead.

Outcome 4 60% · the exam

The seven practices.

Sixty per cent of the paper, roughly 36 of the 60 questions. If your revision time is short, this section is where all of it should go. Formerly called themes; the rename is the clearest signal of whether a resource is current.

How to learn them
For each practice, know four things: its purpose in one line, the management products it produces, which role is accountable, and the defined terms it introduces. Almost every question in this 60% attacks one of those four.

The seven at a glance

PracticeAnswers the questionKey products
Business caseWhy?Business case, benefits management approach
OrganizingWho?Project management team structure, role descriptions, communication management approach
PlansHow, how much, when?Project plan, stage plans, team plans, exception plan, product descriptions
QualityWhat is good enough?Quality management approach, quality register, product descriptions
RiskWhat if?Risk management approach, risk register
IssuesWhat is the impact?Issue management approach, issue register, issue reports
ProgressWhere are we? Should we continue?Daily log, lessons log, highlight reports, checkpoint reports, end stage reports

Business case

Establishes and maintains the justification. Owned by the executive, who is accountable for it throughout. Developed in outline during starting up a project, detailed during initiating a project, and reviewed at every stage boundary, because justification must remain valid, not merely have existed once.

The benefits management approach defines how and when benefits will be measured, and it survives the project: benefits are usually realised after closure, so someone must own their measurement afterwards.

Organizing

Defines the temporary organisation. The structure has four levels, and the exam tests them constantly.

LevelWhoResponsibility
CommissioningCorporate, programme management or the customerSits outside the project, commissions it, sets constraints and appoints the executive.
DirectingProject boardAccountable for the project's success. Makes the go or no-go decisions.
ManagingProject managerRuns the project day to day on behalf of the board, within agreed tolerances.
DeliveringTeam manager and team membersProduces the specialist products to the agreed quality.

The project board holds three roles representing the three stakeholder interests: the executive (business interest, ultimately accountable, and the only role that cannot be shared), the senior user (specifies needs and is accountable for realising benefits), and the senior supplier (provides resources and technical expertise). Project assurance is the board's independent check and cannot be delegated to the project manager. Project support is administrative help and may be shared or delegated.

Plans

PRINCE2 plans are product-based. You define the products first, then the activities needed to create them, then the effort. The four plan types: project plan (the whole, owned by the board), stage plan (one management stage, the project manager's working document), team plan (optional, for a work package), and exception plan (replaces a plan that is forecast to breach tolerance, and is approved at the level that set the tolerance).

Product-based planning has four steps: write the project product description, create the product breakdown structure, write product descriptions, then create the product flow diagram showing the sequence and dependencies.

Quality

Two ideas the exam loves to separate. Quality planning defines what "fit for purpose" means: quality criteria go into product descriptions, and acceptance criteria into the project product description. Quality control checks that products meet them, and records results in the quality register.

Also distinguish quality assurance (an organisational function, independent of the project, checking the project is being run properly) from project assurance (the project board's own independent check). They are different, and questions exploit the similarity.

Risk

A risk is an uncertain event that, should it occur, will affect the achievement of objectives. Risks are threats (negative) or opportunities (positive). The recommended procedure has five steps: identify, assess, plan, implement, with communicate running throughout rather than as a final step.

Responses to threatsResponses to opportunities
Avoid, reduce, transfer, share, accept, prepare contingent plansExploit, enhance, share, reject

Risk owner manages and monitors a risk; risk actionee carries out the response action. They may be the same person but are defined separately, and the exam asks.

Issues

An issue is anything happening now that needs addressing, as opposed to a risk, which might happen. Three types: a request for change, an off-specification (a product that does not or will not meet its specification), and a problem or concern (anything else).

Handled either formally in the issue register, or informally in the daily log if minor. Change authority is the role that decides on requests for change, and a change budget may be set aside to fund approved ones.

Progress

Answers whether the project is on track and should continue. It rests on tolerances (permitted deviation before escalation, set against all seven performance aspects at project, stage and team level) and on regular reporting.

ReportFromTo
Checkpoint reportTeam managerProject manager
Highlight reportProject managerProject board
Exception reportProject managerProject board, when tolerance is forecast to be exceeded
End stage reportProject managerProject board, at a stage boundary
End project reportProject managerProject board, at closure
Outcome 5 15%

The seven processes.

Roughly nine questions. The processes are the timeline: what happens, in what order, and who does it. Learn the purpose of each and which management products it produces, and most questions answer themselves.

The seven, in sequence

ProcessPurposeOwner
Starting up a projectDecide whether the project is worthwhile and viable. Pre-project: it happens before the project is authorised.Executive and project manager
Directing a projectEnable the board to be accountable through key decisions, while delegating day-to-day management. Runs the entire length of the project.Project board
Initiating a projectEstablish solid foundations: agree how the project will be run and produce the PID.Project manager
Controlling a stageAssign and monitor work, deal with issues, report progress within the current stage.Project manager
Managing product deliveryControl the link between project manager and team, and produce the specialist products.Team manager
Managing a stage boundaryReport on the stage just finished, plan the next one, and update the business case so the board can decide whether to continue.Project manager
Closing a projectConfirm the products are accepted and the project's objectives met, then close it in an orderly way.Project manager
Three facts that answer a lot of questions
Starting up a project is pre-project. The project does not formally exist until the board authorises initiation.
Directing a project spans the whole project. It is not a phase; it runs alongside everything from authorisation to closure.
Closing a project is a process, not a stage. It takes place within the final delivery stage rather than as a stage of its own.

The products that mark the boundaries

The two-stage minimum

Every PRINCE2 project has at least two management stages: the initiation stage and at least one delivery stage. That follows directly from the manage by stages principle, and it is a frequent exam check.

The board's decision points sit at stage boundaries, which is what makes stages the control mechanism rather than an administrative convenience.

Reference

Glossary.

The defined terms this exam is built from, grouped so the ones that get confused sit next to each other.

Project
A temporary organisation created for the purpose of delivering one or more business products according to an agreed business case.
Five integrated elements
Principles, people, practices, processes, project context.
Seven performance aspects
Benefits, cost, time, quality, scope, sustainability, risk. Sustainability is new in version 7.
Output / outcome / benefit
What the project delivers / the change that results from using it / the measurable improvement from that change.
Management vs specialist products
Management products run the project (plans, reports, registers). Specialist products are what it was created to deliver.
Seven principles
Continued business justification, learn from experience, defined roles and responsibilities, manage by stages, manage by exception, focus on products, tailor to suit the project.
Seven practices
Business case, organizing, plans, quality, risk, issues, progress. Formerly called themes.
Seven processes
Starting up a project, directing a project, initiating a project, controlling a stage, managing product delivery, managing a stage boundary, closing a project.
Executive
Owns the business case, ultimately accountable for the project. The one project board role that cannot be shared.
Senior user / senior supplier
Specifies needs and is accountable for realising benefits / provides resources and technical expertise.
Project assurance vs quality assurance
The board's independent check on the project (cannot be delegated to the project manager) / an organisational function independent of the project.
Tolerance
Permissible deviation from a plan's targets without escalating, set against all seven performance aspects at project, stage and team level.
Exception
A situation where a tolerance is forecast to be exceeded. Triggers an exception report and possibly an exception plan.
Risk vs issue
Risk might happen; issue is happening now.
Issue types
Request for change, off-specification, problem or concern.
Risk owner vs risk actionee
Manages and monitors the risk / carries out the response action.
Threat responses
Avoid, reduce, transfer, share, accept, prepare contingent plans.
Opportunity responses
Exploit, enhance, share, reject.
Plan types
Project plan, stage plan, team plan, exception plan.
Product-based planning
Project product description, product breakdown structure, product descriptions, product flow diagram.
Project brief vs PID
Output of starting up a project, input to initiation / output of initiating a project, the baseline for the project.
Work package
The agreement between project manager and team manager covering what to produce, to what quality, by when, within what tolerance.
Checkpoint / highlight / exception report
Team manager to project manager / project manager to board, routine / project manager to board, when tolerance is forecast to be breached.
Daily log vs lessons log
Informal record of issues and observations / record of lessons that may apply to this or future projects.
Change authority / change budget
The role that decides on requests for change / funds set aside to pay for approved ones.
Management stage
The section of a project the project manager runs on behalf of the board. Minimum of two: initiation plus at least one delivery stage.
Three delivery approaches
Predictive, agile, hybrid.
Common questions

PRINCE2 7 Foundation exam questions, answered

How many questions are on the PRINCE2 7 Foundation exam?

The PRINCE2 7 Foundation exam has 60 questions and lasts 60 minutes. You need 60% to pass.

What is on the PRINCE2 7 Foundation exam?

The exam covers 5 domains: Key concepts (3%), Principles (8%), People (14%), Practices (60%), Processes (15%). These weightings come from PeopleCert's PRINCE2 7 syllabus.

Is this PRINCE2 7 Foundation material current?

Yes. This guide was written from PeopleCert's own published outline, PRINCE2 7 syllabus, and last checked against that document on 27 July 2026. That date is shown on every page so you can judge for yourself rather than take our word for it.

Are there free PRINCE2 7 Foundation practice questions?

Yes. Sample questions with full worked explanations are free and need no account. The complete question bank and the full-length 60-question timed mock are paid.

Practise it

The guide above is free. The question bank and the full-length timed mock are the paid part.

Open PRINCE2 →
Other exams:
PMP · CAPM · PMI-ACP · PSM I · ITIL · ISTQB CTFL · CC · Network+ · Security+ · CISSP · AWS CCP

Cutscores is independent and is not affiliated with, authorised by, endorsed by or sponsored by PeopleCert or any certification body. PRINCE2 and all certification names and marks are the property of their respective owners, and are used here only to describe which exam this material prepares you for. We do not reproduce live exam content.